4.1 Exterior wall systems require time to design, fabricate, construct and test. Mockups are generally a full-size representative portion of the proposed exterior wall system built to study proposed construction details, test for performance, and in some cases judge appearance of the exterior wall system. The project schedule shall allow time to design, construct, and test the pre-construction mockup and to implement any design changes, fabrication changes, or modifications of planned construction procedures, before construction of the exterior wall system commences.
4.2 Performance testing of pre-construction mockups verifies compliance with specified standards and design criteria. Performance tests in separate ASTM or other industry standards, are intended to represent the effects of environmental conditions, such as wind, rain, and temperature extremes. The tests provide a measure of the performance of the proposed exterior wall system under specific and controlled conditions. The specified design and specification of the pre-construction mockup must be appropriate for the performance test requirements. Separate tests may be required for individual mockup materials or components.
4.3 Pre-construction mockup specimens require input from Specifier, Builder, and Test Agency. Coordination of their efforts facilitates this process. Documentation should convey the results of preconstruction mockups from one party to others at appropriate stages in the process.
4.4 The referenced standards provided in this practice identify the historical standards typically utilized in pre-construction performance testing. This practice allows for the development and use of other project specific test procedures for various components that encompass exterior wall systems.
Область применения1.1 This standard practice covers procedures and documentation to assist in the specification and evaluation of pre-construction laboratory mockups of exterior wall systems.
1.2 This standard practice addresses design and construction of the mockup, observation during mockup construction and testing, evaluation of the mockup test results, and documentation of the mockup and testing process. Coordination is required between the parties involved in the design, construction, and testing of the mockup to facilitate this process. Documentation should convey the results of pre-construction mockups from one party to others at appropriate stages in the process.
1.3 This standard practice recommends the selection and order of individual tests performed on the mockup in the absence of a specific test order.
1.4 This standard practice recommends a protocol for exchange of information between participants in the pre-construction mockup process.
1.5 Responsibility for specific activities is recommended by this practice. This practice is intended to provide a default structure in the absence of the assignment of specific responsibilities by the specifying authority.
1.6 The values stated in inch-pound units are to be regarded as standard. The values given in parentheses are mathematical conversions to SI units that are provided for information only and are not considered standard.
1.7 This international standard was developed in accordance with internationally recognized principles on standardization established in the Decision on Principles for the Development of International Standards, Guides and Recommendations issued by the World Trade Organization Technical Barriers to Trade (TBT) Committee.